On a normal service visit the following checks are made. We recommend that each unit is checked once every 6 months for:-

1.

Operation of all services and system controls.

2.

Filter and seal integrity tests.

3.

Inspection of the door mechanism (if fitted) for corrosion and damage.

4.

Inspection of main body for corrosion and damage.

5.

Check alarm and airflow gauge for correct operation and calibration (if fitted).

6.

Pre filter changed if necessary.


Air inflow measurement - Using - Airflow Developments AV2 Anemometer.
Horizontal/Vertical Laminar Flow unit - Measure airflow, a minimum of eight positions should be used and these should be recorded on the service report.

As per requirements BS5295:1989

Filter and seal integrity tests - Using - Taylor Smoke generator and ATI forward light scattering photometer

Horizontal/Vertical Laminar Flow unit - Determine the penetration of Hepa filters and the integrity of filter seals and cabinet carcass using DOP aerosol and a aerosol photometer to determine the DOP concentration.
As per requirements of Appendix B of BS5726: Part 1:1992. Section 8.5.

Give full test certificate.
All test equipment where necessary is always calibrated and carries a full calibration test certificate.
Any of these certificates are available on special request.